1 budget named it 1 year span ₹ crore allocated 236 ₹ crore whole-project cost DMK government

First announced in 2011-12 and not named in any budget since.

See it on the map → All Urban projects →

What each budget said, year by year

2011-12 ` 236 crores continuation project cost DMK · interim

“Under the Anaithu Peruratchi Anna Marumalarchi Thittam, over the past three years works amounting to ` 236 crores have been carried out in 420 town panchayats. During current financial year, works at an estimated cost of ` 88 crores are being executed in the remaining 139 town panchayats.”

tnbudget_2011-12_speech_en_interim · p.33 · ¶84 · source PDF ↗ · on the map →