DRIP-II project

1 budget named it 1 year span ₹ crore allocated 610 ₹ crore whole-project cost AIADMK government

First announced in 2019-20 and not named in any budget since.

See it on the map → All Irrigation projects →

What each budget said, year by year

2019-20 Rs.610.26 crore new project project cost AIADMK

“The Government of Tamil Nadu has also accorded approval for the DRIP-II project under which it is proposed to rehabilitate and improve 37 dams and associated appurtenances. The project will be taken up at a cost of Rs.610.26 crore which will be completed in a span of five years from 2020-2021.”

tnbudget_2019-20_speech_en · p.28 · ¶44 · source PDF ↗ · on the map →