BSUP / Integrated Housing and Slum Development Programme

1 budget named it 1 year span ₹ crore allocated 2,843 ₹ crore whole-project cost DMK government

First announced in 2011-12 and not named in any budget since.

See it on the map → All Housing projects →

What each budget said, year by year

2011-12 ` 2,843 crores continuation project cost DMK · interim

“Action has been initiated to construct tenements consisting of 1,28,906 units and improve basic infrastructure in Slums at an estimated cost of ` 2,843 crores, over the past five years under Basic services to Urban Poor, Integrated Housing and Slum Development Programme which are sub components within the Jawaharlal Nehru National Urban Renewal mission.”

tnbudget_2011-12_speech_en_interim · p.31 · ¶77 · source PDF ↗ · on the map →